Name: | ALPHA CONTRACTING & ASSOCIATES LLC |
Jurisdiction: | MISSISSIPPI |
Business Type: | Limited Liability Company |
Status: | Good Standing |
Effective Date: | 14 Feb 2017 (8 years ago) |
Business ID: | 1111203 |
ZIP code: | 39402 |
County: | Lamar |
State of Incorporation: | MISSISSIPPI |
Principal Office Address: | 23 SEQUATCHIE Hattiesburg, MS 39402 |
Type | Company Name | Company Number | State |
---|---|---|---|
Headquarter of | ALPHA CONTRACTING & ASSOCIATES LLC, ALABAMA | 000-948-304 | ALABAMA |
Name | Role | Address |
---|---|---|
GELGA PAOLA PEREZ-GUILLERMO | Agent | 23 SEQUATCHIE LN, HATTIESBURG, MS 39402 |
Name | Role | Address |
---|---|---|
GELGA PAOLA PEREZ-GUILLERMO | Manager | 23 SEQUATCHIE LN, HATTIESBURG, MS 39402 |
Type | Status | Filed Date | Description |
---|---|---|---|
Annual Report LLC | Filed | 2025-02-10 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2024-04-04 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2023-04-22 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2022-02-07 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2021-06-21 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2020-02-08 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2019-08-16 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Annual Report LLC | Filed | 2018-04-16 | Annual Report For ALPHA CONTRACTING & ASSOCIATES LLC |
Formation Form | Filed | 2017-02-09 | Formation For ALPHA CONTRACTING & ASSOCIATES LLC |
Inspection Nr | Report ID | Date Opened | Site Address | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
346203912 | 0419400 | 2022-09-08 | 217-219 MONTAIGN DRIVE, VICKSBURG, MS, 39180 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Citation ID | 01001A |
Citaton Type | Other |
Standard Cited | 19101200 E01 |
Issuance Date | 2022-09-20 |
Abatement Due Date | 2022-10-13 |
Current Penalty | 0.0 |
Initial Penalty | 0.0 |
Final Order | 2022-10-19 |
Nr Instances | 1 |
Nr Exposed | 3 |
FTA Current Penalty | 0.0 |
Citation text line | The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: 217-219 Montaign Drive, Vicksburg, MS 39180: (a) On or about 9/8/2022, the employer did not develop or implement a written hazard communication program for employees exposed to hazardous chemicals such as spray paint and diesel fuel. |
Citation ID | 01001B |
Citaton Type | Other |
Standard Cited | 19101200 G08 |
Issuance Date | 2022-09-20 |
Current Penalty | 0.0 |
Initial Penalty | 0.0 |
Final Order | 2022-10-19 |
Nr Instances | 1 |
Nr Exposed | 3 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1910.1200(g)(8): The employer did not maintain in the workplace copies of the required safety data sheets for each hazardous chemical, and did not ensure that they were readily accessible during each work shift to employees when they were in their work area(s) 217-219 Montaign Drive, Vicksburg, MS 39180: (a) On or about 9/8/2022, the employer did not ensure that copies of safety data sheets were readily accessible at the worksite for employees exposed to spray paint and diesel fuel. |
Citation ID | 01001C |
Citaton Type | Other |
Standard Cited | 19101200 H01 |
Issuance Date | 2022-09-20 |
Current Penalty | 0.0 |
Initial Penalty | 0.0 |
Final Order | 2022-10-19 |
Nr Instances | 1 |
Nr Exposed | 3 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1910.1200(h)(1):Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: 217-219 Montaign Drive, Vicksburg, MS 39180: (a) On or about 9/8/2022, the employer did not ensure that employees exposed to hazardous chemicals such as spray paint and diesel received training |
Citation ID | 01002 |
Citaton Type | Other |
Standard Cited | 19260651 J02 |
Issuance Date | 2022-09-20 |
Abatement Due Date | 2022-10-13 |
Current Penalty | 0.0 |
Initial Penalty | 0.0 |
Final Order | 2022-10-19 |
Nr Instances | 1 |
Nr Exposed | 1 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.651(j)(2):Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary. 217-219 Montaign Drive, Vicksburg, MS 39180 (a) On or about 9/8/2022, the employer did not ensure that employees who were working in trenches were protected from debris rolling into excavations by placing the excavated material at least 2 feet from the edge of the excavation or by the use of retaining devices. |
Date of last update: 31 Mar 2025
Sources: Mississippi Secretary of State